History

2023
2022
2021
2020
2019
2018
2017
2016
2015
2014
March

Fourth shipment of HMC completed at Coburn Project

 

February

Tanzanian Project tenements re-issued to Nyati JV

Third shipment of HMC completed at Coburn Project

 

January

Second shipment of HMC completed at Coburn Project

December

20 December 2022 – First shipment of HMC Completed at Coburn Project

 

November

22 November 2022 – 2022 Sustainability Report

18 November 2022 – Commercial Production of HMC achieved at Coburn Project

2 November 2022 – First ore Processed in Wet Concentrator at Coburn Project

 

October

13 October 2022 – Coburn Project Water Commissioning of WCP Underway

 

June

7 June 2022 – Coburn Project Construction Progress Reaches 75% Complete

 

April

4 April 2022 – Coburn Project Production Capacity Upgrade Study Initiated

 

March

22 March 2022 – Tajiri Project Environmental Approval Received

December

14 December 2021 – Framework Agreement Signed with the Government of Tanzania

 

November

22 November 2021 – Coburn Project Product Logistics Services Contract Awarded

 

October

18 October 2021 – Inaugural Sustainability Report 2021

4 October 2021 – Coburn Project Mining Services Contract Awarded

1 October 2021 – Financial Close Achieved

 

June

1 June 2021 – NAIF Loan Facility Reaches Contractual Close

 

May

19 May 2021 – Coburn Binding offtake Contract Signed for Premium Zircon

4 May 2021 – Coburn Final Investment Decision Approval

 

April

29 April 2021 – Primero to Build Process Plant

27 April 2021 – LNG Supply Agreement with Woodside-EDL Joint Venture

6 April 2021 – Coburn now fully funded to Production

 

March

9 March 2021 – Electricity Supply Agreement with Contract Power

3 March 2021 – Coburn Mineral Sands Project – Binding Rutile Offtake Contract

November

16 November 2020 – Port Access Secured for Coburn’s Mineral Sands Products

5 November 2020 – Coburn Mineral Sands Project – LNG Supply for Power Generation – Woodside-EDL JV Appointed

4 November 2020 – Coburn Minerals Sands Project – Power Facility Build Own Operate Contract Power Appointed

 

October

7 October 2020 – Tajiri Engineering Scoping Study

 

September

29 September 2020 – Primero Group Appointed as Preferred Contractor to Build Coburn Processing Facilities

14 September 2020 – Piacentini Awarded Supply Contract for Coburn Development

 

August

6 August 2020 – Strandline Receives firm commitments for $18.5m in Share Placement

3 August 2020 – Contract Award Civil Bulk Earthworks Construction

 

July

2 July 2020 – Another Binding Sales Contract for Coburn Project

 

June

22 June 2020 – NAIF Loan Facility Approves $150m for Coburn Project in WA

4 June 2020 – Coburns NPV increases by 28% to $705 million, with average annual EBITDA of $104 million

 

May

18 May 2020 – Independent Expert Reports Reaffirm Coburn’s Robust Fundamental

 

April

30 April 2020 – Macmahon Appointed Preferred Mining Contractor for the Coburn Mineral Sands Project in WA

20 April 2020 – Three Binding Offtake Contracts signed for Coburn

6 April 2020 – US$26m Project Finance Facility Agreement signed for Fungoni Mineral Sands Project

 

March

23 March 2020 – Successful Completion of $6.5m Raising

 

January

14 January 2020 – Outstanding Test Results Strengthen Coburn Financial Outlook

December

3 December 2019 – Coburn Power Deal with Woodside-EDL Power Solution

 

October

9 October 2019 – Key Steps Towards Securing Coburn Funding from NAIF

 

September

25 September 2019 – Tajiri New Sakura Discovery

 

July

9 July 2019 – Tajiri confirmed as a world-scale mineral sands deposit with 80% Resource increase to 268Mt

 

June

17 June 2019 – Strandline secures Credit Approval for US$26m Project Finance Facility for Fungoni development

 

May

24 May 2019 – Strandline raises $5.5m to advance key mineral sands projects in WA and Tanzania

 

April

16 April 2019 – Definitive Feasibility Study shows Coburn will generate strong financial returns over a long life

1 April 2019 – Outstanding improvements in process recoveries from Coburn DFS

 

March

27 March 2019 – More thick intersections point to large mid-year Resource increase at Tajiri minerals sands project

 

January

3 January 2019 – Nedbank CIB mandated for Fungoni Project Financing

December

Coburn Mineral Resource Estimate increases to 1.6Bt

 

November

Sudi Project JV with Rio Tinto to drill priority targets
Fungoni Project – Updated DFS

 

October

Coburn Project – DFS Update
Fungoni Project – Rutile Offtake Signed

 

September

Exploration update – Bagamoyo Project

 

August

Fungoni Mining Licence Approved

 

June

Strandline appoint leading industry specialists to advance the DFS for Coburn mineral sands project

New thick zones of mineral sands pave way for a significant increase in Resources at Tajiri

Strandline starts Definitive Feasibility Study on Coburn mineral sands project in WA

 

May

Binding offtake agreement signed for Fungoni project’s ilmenite

 

April

Major Shareholders Exercise Options Early
Government of Tanzania Announces New Mining Commission
Major Shareholder Increases Equity Position
Major Shareholder Increases Equity Position

 

March

Strong Drilling Results Highlight Growing Potential of Bagamoyo Mineral Sands Project
Significant New Mineral Sands intersections at the Sudi Project

 

February

Tajiri Mineral Sands Resource more than Doubles to 147Mt, establishing a Project of Large Scale

 

January

Binding Offtake Agreement Signed for 100% of Fungoni Project’s Zircon Product

November

Chairman’s Address to Shareholders
Development Strategy for Coburn Mineral Sands Project in WA

 

October

New Mineral Sands Discoveries at Bagamoyo, Tanzania

 

September

Submission for Fungoni Mining Licence Application

 

August

High-Grade Results Point to Resource Increase at Tajiri

July

Key Environmental Approval Secured for Fung9n HMS Project
Fully Funded for Fungoni DFS & Extensive Exploration
Tanzanian Natural Resources Legislative changes

 

June

Rio Tinto Joint Venture Update
Consolidation/Split

 

May

Share Placement to Strategic Investors to Raise $5.2M
High Value Fungoni Mineral Resource Continues to expand

 

April

Rio Tinto Earn-in and Joint Venture Agreement Signed

 

March

Strong Progress on Fungoni Heavy Mineral Sands Project
Mount Gunson Copper-Cobalt Project

 

February

New Mineral Sands Discovery and Extensions at Tanga South

 

January

Fungoni Mineral Sands Project Study Ramps Up
45% increase in Fungoni Mineral Resource estimate to 16Mt @ 3.1% THM

November

Tanga Regional Drilling Demonstrates Potential HMS Scale

Fungoni Drilling Confirms High Grade Core and Extensions

 

October

Progressing Exploration Activities Across Priority Targets

 

September

Appointment of MD/CEO to Drive Project Development Plans

 

May

Strategic Relationship and Subscription Agreement entered into with Tembo Capital

 

April

Maiden Mineral Resource at Tanga South Project in Tanzania

 

February

Positive Scoping Study results for Fungoni Project in Tanzania

December

Sale of Mount Gunson Copper Project

 

October

Acquisition of Jacana Resources (Tanzania)

 

February

Significant CAPEX & OPEX reductions for Coburn Mineral Sands Project

December

Change of Name to Strandline Resources Limited (ASX: STA)

 

October

Acquisition of dominant mineral sands position in Tanzania

Western Areas to farm-in to Fowlers Bay Nickel Project